All ISM-Approved Semiconductor Projects — Status & Timeline

Every semiconductor project approved under India's ISM — from announcement to operations. Investment, location, technology node, current status, and what each facility actually produces. Updated as of July 2026.

13Total approved
3Operational (2026)
3Under construction
7+Approved / pre-build
6States with projects
₹1.6L CrTotal investment committed
Operational
Under construction
Approved / pre-build
Stalled / uncertain
Operational
Feb 28, 2026
Micron Technology — Sanand ATMP
USD 2.75B · Sanand, Gujarat · DRAM and NAND flash memory packaging and test · PM Modi inaugurated · First PM-inaugurated semiconductor facility in India · Memory test engineers hired locally from Ahmedabad / Sanand catchment
DRAM NAND Memory ATMP Gujarat Sanand
Operational
Mar 31, 2026
Kaynes Semicon — Sanand OSAT
₹3,307 crore · Sanand, Gujarat · IPM (Integrated Power Management) devices and power semiconductors · 6.3 million chips per day at full capacity · Wire bonding and encapsulation focus · Second PM-inaugurated semiconductor facility
IPM Power Devices Wire Bonding Gujarat Sanand
Operational
Jul 4, 2026
CG Semi — Sanand OSAT
₹7,600 crore · Sanand, Gujarat · Three-way JV: CG Power (India) + Renesas Electronics America (Japan) + Stars Microelectronics (Thailand) · QFN, QFP, FC-BGA, FC-CSP packages · Automotive, industrial, 5G, IoT, power · G2 plant under construction (combined 15M chips/day) · Third PM-inaugurated facility of 2026
FC-BGA QFN Automotive 5G Renesas Sanand
Under construction
2025–2026
Tata TSAT — Jagiroad ATMP
₹22,916 crore (largest ISM project) · Jagiroad, Assam · Memory and logic ATMP · Tata Semiconductor Assembly and Test · Northeast India cluster anchor · Target: first operations 2026-27
Memory Logic ATMP Assam Jagiroad Tata
Under construction
2025–2027
Tata Electronics (PSMC) — Dholera Fab
USD 11 billion · Dholera, Gujarat · India's first commercial logic fab · TSMC-derived technology via PSMC (Taiwan) · 28nm node, future roadmap to advanced nodes · ASML framework agreement signed May 2026 for EUV/DUV equipment · First silicon targeted late 2026 · Full production ~2028
28nm Logic Fab PSMC ASML Dholera Gujarat
Under construction
Apr 2026
3D Glass Solutions — Bhubaneswar OSAT
ISM FSA signed · Bhubaneswar, Odisha · India's first heterogeneous integration packaging facility · Glass substrates for AI, HPC, defence, and 5G chips · 3DGS US subsidiary (Heterogeneous Integration Packaging Solutions Pvt. Ltd.) · Groundbreaking April 2026
Glass Substrate 3D Integration AI Chips Odisha Heterogeneous
Approved
2025
Tata Electronics — Oragadam Compound Semi
Oragadam, Tamil Nadu · Compound semiconductor fab · SiC, GaN, power devices · Strategic for EV, 5G, and defence electronics
SiC GaN Compound Semi Tamil Nadu Power Devices
Approved
May 2026
Sancode Semi — Odisha OSAT
₹1,650 crore · Odisha · Conventional OSAT packaging · Complements 3DGS advanced packaging in same state
OSAT Odisha Packaging
Approved
2025
Suchi Semicon — Gujarat
Gujarat · ATMP/OSAT · Part of Gujarat's six-project ISM cluster
ATMP Gujarat
Approved
2025
Crystal Matrix — Gujarat
Gujarat · OSAT · Part of Gujarat's six-project ISM cluster
OSAT Gujarat
Approved
May 2026
Cabinet approvals — two more units
Cabinet approved two additional semiconductor manufacturing units in May 2026 · Combined investment >₹3,900 crore · Full details to be published post-FSA signing
Cabinet 2026 Pending Details
Approved
2025
Rajasthan first semiconductor plant
Rajasthan — first semiconductor manufacturing unit approved for the state · ISM support confirmed May 2026
Rajasthan New State
Stalled
2022–2023
ISMC (Intel + Tower Semi) — Karnataka
USD 3 billion announced · Karnataka · Intel-Tower Semiconductor (Israel) partnership · Tower Semiconductor acquisition by Intel failed (US regulatory block, Aug 2023) · Project effectively stalled; no FSA confirmed; MeitY has not announced cancellation
Intel Tower Semi Karnataka Stalled
geography

Which states have ISM-approved projects

Gujarat
6 projects
Micron · Kaynes · CG Semi · Tata-PSMC Dholera · Suchi · Crystal Matrix
Largest ISM cluster globally
Assam
1 project
Tata TSAT Jagiroad
Largest single ISM investment (₹22,916 Cr)
Odisha
2 projects
Sancode Semi · 3D Glass Solutions
Only state with both advanced and conventional OSAT
Tamil Nadu
1 project
Tata Compound Semi Oragadam
SiC/GaN focus
Rajasthan
1 project
Undisclosed — first for state
May 2026 Cabinet approval
Karnataka
Stalled
ISMC (Intel-Tower) stalled
No FSA signed